Pitch Development Stages

  • Stage 1: Level old Pitch and Putt field [COMPLETED]
  • Stage 2: Dressing Rooms [COMPLETED]
  • Stage 3: Entrance Path and Fence Boundary [COMPLETED]
  • Stage 4: Dugouts and Public Path around Pitch [incomplete]